To ensure compliance, it is important to record refrigerant use as soon as possible. The easiest way to do that is from the field by using the SC Provider mobile app. We recommend that you record refrigerant usage at the time of use.
Adding Refrigerant to a Work Order via ServiceChannel Provider
When you are requested to repair or replace refrigerated or HVAC assets, you might need to add, remove, or replace the refrigerant gas. In SC Provider, you can capture refrigerant usage as part of the work order flow.
The infographic below depicts key aspects of recording refrigerant usage covered in this article.
Image Added
When Can You Record Refrigerant Usage?
There are two ways for you to record refrigerant usage:
When you edit a work order, you can specify the refrigerant part(s) you used.
Section |
---|
Column |
---|
| Image Added |
Column |
---|
| Image Added |
|
When you check out of a work order, the refrigerant flow gets triggered.
Section |
---|
Column |
---|
| Image Added |
Column |
---|
| Image Added |
|
Technician Certification
To service HVAC and refrigerated assets, your client may require you to have refrigeration certification. When you answer Yes to the “Did you use refrigerant?” question, the app checks whether your account is associated with a refrigeration certification. This certificate should be uploaded by your manager in Provider Directory (aka Fixxbook).
When refrigeration certification is a requirement on your client’s side, without the uploaded certificate, you will not be able to capture refrigerant usage on work orders.
Note |
---|
Contact your administrator to get the certificate uploaded in Provider Directory. |
Image Added
Answering the “Did You Use Refrigerant?” Question
The app will prompt you to specify whether you used any refrigerant to complete the work. There are three answer options you can choose from when responding to the “Did you use refrigerant?” question.
Note |
---|
Enter Later is an additional option that gets added to the refrigerant flow by request. Contact ServiceChannel to start using it. Image Added |
Section |
---|
Column |
---|
| Yes
Opt for this option if you used the refrigerant part and you are ready to provide the required refrigerant data onsite. If the quantity used meets or exceeds the leak rate threshold, you will be prompted to complete a leak record. |
Column |
---|
| No
If no refrigerant was added, all you need to do is to enter any non-refrigerated parts (if required) and close the work order. |
Column |
---|
| Enter Later
If you are unable to provide the required information onsite and prefer recording refrigerant usage from your home office, pick Enter Later. The work order will be put into the Completed / Pending Refrigerant Use status. Work orders in this status cannot be invoiced until the refrigerant data is entered. Techs will not be able to enter the refrigeration information in SC Provider. The refrigeration information will have to be provided via Provider Automation. |
|
Where Did You Take Refrigerant Parts From?
Recording refrigerant usage against a work order implies that you, first of all, specify the location, aka the source location, where you took the required refrigerant gas from.
Image Added
Client’s inventory: When a refrigerant part is taken from the client’s location inventory, pick the required inventory location from the locations list. Note that the app will show only those inventory locations to which you are assigned by your client.
Note |
---|
Based on your client’s preferences, you may have either full or limited access to inventory locations. Thus, the app may show either all inventory locations or only the ones in the technician’s area. |
Work order location: If the work order location stores inventory, it will appear at the top of the list.
Vendor supplied: To add non-inventory refrigerant parts, pick the Vendor Supplied option, and enter the required refrigerant data manually.
Completing a Leak Record
Taking into account the quantity of the refrigerant used and the usage reason, the app will calculate the leak rate.
Section |
---|
Column |
---|
| Image Added |
Column |
---|
| Image Added |
|
Whenever the leak rate on a work order meets or exceeds the leak rate threshold and the use reason is set to Unknown, Leak, or Repair, you are asked to complete a leak record. The purpose is to collect comprehensive data on the leak and stay compliant with the local and governmental regulations.
To complete a leak record and move it to the Closed status, you are required to fill out all the fields marked with a pencil icon 🖉 on the Leak Record screen. If you complete the leak record partially or skip that step at all, the leak will stay in the Open status. You might not be able to invoice the work order until the leak record is closed.
Section |
---|
Column |
---|
| Image Added |
Column |
---|
| Image Added |
|
Info |
---|
Skip: You can skip this step if you cannot provide the requested information onsite. Note that, in this case, the leak will stay in the Open status. Done: When at least one field is filled out on the Asset Record screen, you are allowed to tap Done and proceed. If you do not complete all the fields via the SC Provider mobile app, you can close the leak record via Provider Automation. The leak stays in the Open status until all the required information is entered. Based on your client’s preferences, you may not be able to invoice the work order with an open leak.
|
How to Record Refrigerant Use on a Work Order in SC Provider
Panel |
---|
bgColor | #F9F9F9 |
---|
titleColor | #0e3367 |
---|
titleBGColor | #EAEAEA |
---|
borderStyle | none |
---|
title | ⦿ How to Record Refrigerant Use on a Work Order via SC Provider |
---|
|
Locate the desired work order .- Tap Accept.
Image Removed - Tap Log Time, to start the work order clock.
Image Removed - Tap Repair, to indicate that you are beginning to work on the work order.
- When the work order is complete, tap Stop.
Image Removed - Select one of the available statuses, then tap Done.
Image Removed - Add a Work Summary, then tap Submit.
Image Removed - When prompted, "Did you use refrigerant" tap Yes.
Image Removed
Note | Note: If the technician selects Enter Later, the refrigeration usage will have to be entered via Provider Automation, because the technician will no longer have access once they close the work order. , and check in to it by tapping Check In. Once you complete your work, tap Check Out, and then choose a work order status. Pick resolution codes and a root cause. Confirm using refrigerant on the work order by selecting Yes. Image Added Note |
---|
You may see the Enter Later option in the Did you use refrigerant? pop-up window that allows you to enter refrigerant use later. In this case, only users who have access to Provider Automation can specify this information at a later time. |
Pick an asset on which you used refrigerant, and then tap Done. On the Update Usage screen, tap Add Part.
On the Choose Source Location screen, select the location where the part originates from. Note |
---|
Note: As an external provider, you will only see client inventory for the location the work order is assigned to. | Image Removed- Select the Refrigerant used from the available list.
Image Removed - Enter the Quantity used in pounds and ounces
From the list of parts, select the refrigerant part used. Image Added Enter the part Quantity used, then select the Reason why the refrigerant was added. Image Removed Note |
---|
If Unknown, Leak, Leak or Repair are is chosen as the reason for the addition of refrigerant, and the amount added is sufficient, then the EPA Leak Record Calculation is done. If the leak record calculation breaches the established threshold, then additional information is required. |
For each section where there is a red asterisk, select the appropriate value. On the Leak Record screen, fill out the fields marked with a pencil icon. Then enter a leak record note, and tap Done. Note |
---|
The sections must be completed in the order in which they are listed , as because subsequent section sections are dependent on the response entered into in the previous section. |
Enter a Description of Work, then tap a work order summary, and tap Submit.
Review the work order, then tap Done. Image Removed
The work order status is now complete changed, and the required Refrigeration information has been added.information on refrigerant used is added. |
Adding Refrigerant to a Work Order in Provider Automation
Panel |
---|
bgColor | #F9F9F9 |
---|
titleColor | #0e3367 |
---|
titleBGColor | #EAEAEA |
---|
borderStyle | none |
---|
title | ⦿ How to Record Refrigerant Use on a Work Order via Provider Automation |
---|
|
Locate the desired work order, then click Enter Refrigerant Usage.
Note |
---|
Note: The work order should be in the status of Completed/Pending Refrigerant Use. |
Image RemovedImage Added - Select the technician who used the refrigerant on the work order.
Select the asset from the list, then click the Save and Next button. Note |
---|
Note: If the asset is to be repaired, select the Repair radial button. |
Image Modified
On the Refrigerant Tracking screenTracking screen, first select whether the refrigerant was taken from Internal Inventory or Vendor Supplied.
Note |
---|
Note: You must first indicate where the inventory was taken from, as this effects affects other selections. |
From Internal Inventory: Select the Part Number from the dropdown drop-down list ;. Add the Amount of refrigerant used in pounds and fractions or pounds and ounces;. Add a Part Description ;. Select the Date the refrigerant was used ; . Select the Reason why the refrigerant was used;. Note |
---|
If Unknown, Leak, Leak or Repair are is chosen as the reason for the addition of refrigerant and the amount added is sufficient, then the EPA Leak Record Calculation is done. If the leak record calculation breaches the established threshold, then additional information is required. |
Image Modified Add another part, if necessary. If you do not need to add another part, click the Next button;. Note |
---|
Note: If the amount of refrigerant used was sufficient enough to exceed the leak threshold, a Leak Record will be created for the asset. |
Complete the Leak Record , .Then click the Next button ; and. Image Modified Add a descriptionnote, the then click the Save button. Image Modified The work order 's status has changed from moves to the Completed / Pending Refrigerant Use to Completed/Pending Confirmation status. Image Modified
From External Inventory: Add the Part Number used ;. Add the Amount of refrigerant used in pounds and fractions or pounds and ounces;. Add a Part Description ;. Select the Date the refrigerant was used ;. Select the Reason why the refrigerant was used; . Image Modified Note |
---|
If Unknown, Leak, Leak or Repair are is chosen as the reason for the addition of refrigerant and the amount added is sufficient, then the EPA Leak Record Calculation is done. If the leak record calculation breaches the established threshold, then additional information is required. |
Add another part, if necessary. If you do not need to add another part, click the Next button;. Note |
---|
Note: If the amount of refrigerant used was sufficient enough to exceed the leak threshold, a Leak Record will be created for the asset. |
Complete the Leak Record, .Then click the Next button; and. Image Modified Add a descriptionnote, the then click the Save button. Image Modified The work order 's status has changed from moves to the Completed / Pending Refrigerant Use to Completed/Pending ConfirmationConfirmation status. Image Modified
|